|
Project
Management Tool No. 1: The Work
Breakdown Structure (WBS) Way
to Better Project Effort Estimation
& Budgeting
Here's
a quick summary of the PMP®-standard
project estimating process:
First
and foremost, you need to lay
out a network diagram known as
a 'work breakdown structure' (WBS).
The WBS is intended to define
all discrete project tasks that
require at least x hours
of work to complete; the x
figure can vary depending on size
of project, desired accuracy of
estimate, etc.
For
an IT consultancy, for example,
for which discrete amounts of
hours must be accounted for and
billed, you might want to make
x = 8 hours for a granular WBS.
However this value can and should
be adjusted as desired, and generally
the lowest level is set at 80
hours. Too much or too little
detail in a WBS can actually diminish
its usefulness and accuracy.
Here's
how to develop your WBS and take
the basic steps required to help
you estimate how much time and
money you'll need for your project:
- Project
Manager and/or other 'project
leader'/experts develop(s) first-round
WBS outlining main categories
of work to be done, with as
many tasks detailed as much
as possible in that first-round
draft.
- PM
meets with likely project team
members, explains overall Goal
and Objectives of project, and
reviews first-draft WBS, adding
more detailed tasks to it and
revising others based on team
member input. Once the WBS is
further detailed, PM solicits
team member input on effort
estimates (time to finish each
defined task). PM should solicit
one time estimate for tasks
that are relatively 'known'
or well-defined; for more unknown
tasks or ones that the team
are less certain of estimating,
solicit three time estimates
(Optimistic, Most Likely, and
Pessimistic), which will be
used later to calculate a single
time estimate (see Step 4).
A well-organized 1-hour meeting
with likely project team members
should be sufficient to solicit
both more specific tasks for
the WBS and time estimates for
all defined WBS tasks.
- (Optional:
Review WBS and initial time
estimates with other PMs/project
leaders and/or subject-matter
experts to identify any missing
elements and/or to refine estimates
and tasks as necessary. If extensive
revision on the WBS is done
here, the PM will have to hold
another meeting with likely
project team members to solicit
revised estimates for revised
tasks and/or new estimates for
new tasks.)
- For
'uncertain/unknown' tasks, PM
uses PERT formula to identify
one most likely task time estimate
(Optimistic + (4 x Most Likely)
+ Pessimistic)/6. PM now has
a single time estimate for all
defined project tasks. These
estimates can be combined to
estimate the entire effort necessary
to execute on the project in
terms of total number of man
hours required. A well-done
WBS also indicates likely expenses
for equipment and materiel as
well, which, when added to labor
estimates, give you a better,
more accurate project budget
and baseline.
There
you go, just four steps and you're
on your way to better project
planning! And in addition to having
more accurate time estimates,
the PM now also has the information
necessary to diagram the project
in terms of which tasks should/have
to take place when (i.e., prototyping
after requirements-gathering,
development after development
environment set-up). Once the
project task precedence is diagrammed,
early and late start and finish
dates can be calculated, and the
project's critical path can be
identified.
If
you do the WBS in Microsoft Project,
you can use it to immediately
generate Gantt charts that may
be useful in internal or external
sales efforts, in addition to
setting up a range of tools for
project progress tracking and
reporting.
V
<Back
to On Target Topic Index
|